the bedroom that costs $200,000
water service is sized in steps, not by the fixture. this page adds up a small project's fixture units, shows which meter and service size it lands on, and draws where the next step is - and what one more bathroom or one more unit does to it.
the project
fixture unit values - edit to match the adopted table
| fixture | WSFU, private use | used for | status |
|---|---|---|---|
| bathtub or tub/shower combo | full bath, extra bedrooms | verify | |
| shower stall | full bath, if chosen above | verify | |
| lavatory | every bath | verify | |
| water closet, flush tank | every bath | verify | |
| kitchen sink | per unit | verify | |
| dishwasher | per unit | verify | |
| clothes washer | per unit | verify | |
| hose bibb | per unitUPC counts each bibb after the first at 1.0 - not modeled, runs high | verify |
meter and service bands - edit to match the utility's letter
| meter | service line | up to (WSFU) | cost to step past this band ($) | status |
|---|---|---|---|---|
| 3/4 in | 3/4 in | verify | ||
| 3/4 in | 1 in | verify | ||
| 1 in | 1 in | verify | ||
| 1 in | 1-1/4 in | verify | ||
| 1 in | 1-1/2 in | verify | ||
| 1-1/2 in | 1-1/2 in | verify | ||
| 2 in | 2 in | verify |
the band limits were read from a printed 2016 CPC copy of UPC table 610.4, 46-60 psi column at 100 ft of developed length (17 / 33 / 36 / 67 / 85 / 151 / 370). the table keeps only the rows where the meter and the line grow together and leaves out the mixed sizes the print also lists (3/4 in meter on a 1-1/4 in line at 39, 1-1/2 in meter on a 1-1/4 in line at 78, 1-1/2 in meter on a 2 in line at 318), so between 151 and 318 WSFU the print may allow a smaller meter than this page shows. Austin adopted the 2021 UPC; the 2021 print was not fetched, so confirm it matches before relying on any row. the step costs are assumptions: $8,000 for a 3/4 to 1 in meter step, reused for the three service-line-only steps; $35,000 for the 1 to 1-1/2 in meter step; $90,000 for 1-1/2 to 2 in. past the last band, or wherever the required service line is bigger than the existing one, the site-to-street line upsize above is added.
where this project lands
| scenario | WSFU | meter / service | added cost |
|---|
checks - the numbers behind the claims
read this before using any of it
the cliff is real, and it is about capacity thresholds, not fixtures. a utility does not price the bathroom. it prices the meter and the pipe the bathroom pushes you onto, and those come in fixed sizes. the fixture that crosses the line pays for the whole step, and if the step is a bigger service line, the step runs from the meter box back to the main in the street.
find out before the unit mix is locked. the panel's example was one added bedroom. the cheapest question on a small infill project is a capacity read from the utility while the plan is still a sketch. after the pro forma is built around a bedroom count, the answer is either a redesign or a six-figure line item that was not in the budget.
the city is piloting early utility coordination. Austin is trying upfront coordination of water, electric, street trees, sidewalk and curb on its own capital street projects. it has not reached private residential permitting yet. until it does, the coordination is the project's job, and this page is a way to start the conversation with a number instead of a guess.